DBHYDRO       reports

Hydraulic Details

SitePumped WellX-Coord(ft)Y-Coord (ft)
CLEWISTON RO WELLFIELDCLEWRO-PW2675831875040

Start Test Date:13-DEC-2005 0000Aquifer:UPPER FLORIDAN AQUIFER (UFA)
Test Type:APTTransmissivity (ft2/day):12800
Discharge Rate (gal/min):964Horizontal K (ft/day):
Hours Pumped:48Vertical K (ft/day):
Tested Interval Min. (ft BLS):700Storativity:.00043
Tested Interval Max. (ft BLS):1200Leakance (1/day):.0008
No. Monitored Wells:2Specific Capacity (gpm/ft):
SourceReferenceCitation Id
  CDM, 2006. CITY OF CLEWISTON WATER TREATMENT PLANT PRODUCTION WELLS PW-1 AND PW-2, COMPLETION REPORT. APRIL 2006.
Comments:PUMP FAILED AFTER 2 DAYS OF PUMPING, NO COLLECTION OF RECOVERY DATA. CHLORIDE CONCENTRATION AT END OF TEST = 1140 MG/L.